During CAM preparation of a 6-layer HDI order classified as 2-order, our team identified two data items that required explicit customer confirmation before drill and lamination tools could be released. The board measures 68 mm by 116 mm, uses Kingboard KB-6165F FR-4 with TG150, is specified at 1.0 mm finished thickness with 1 oz copper on outer and inner layers, carries blue solder mask and white silkscreen, and requires resin plugging of vias. Blind and buried vias are indicated, the minimum hole size is listed as 0.15 mm, separation combines V-cut and routing, and the delivery format is customer self-panelization in a 1×2 array with no process edge. Mechanical forming is specified and no impedance control is required. These parameters establish a compact 2-order HDI construction in which the active drill set and the sequential stackup must be unambiguous.
The main engineering questions asked whether the drill holes contained in a TXT4 file could be ignored, given that the drill-report (DRR) data appeared on TXT3, and whether the factory-prepared stackup structure was acceptable. The customer replied that the TXT4 file was obsolete and should be ignored, and confirmed that the attached stackup was acceptable.
HDI Drill File Verification: Excluding the Obsolete TXT4 File
The Gerber package contained both a TXT3 layer, on which the drill-report data were shown, and a separate TXT4 drill file. We asked the customer to confirm whether the holes in TXT4 could be ignored. In HDI data sets it is not uncommon for earlier revisions or temporary drill files to remain in the folder; if an obsolete file is processed, extra holes may be drilled, plated, and resin-plugged, creating unintended openings or consuming process capacity on a board whose minimum hole size is already 0.15 mm.

Figure 1: DRR are shown on this layer TXT3

Figure 2: There is TXT4 drill file in the gerber file
The customer's reply stated that TXT4 was an old file and should be ignored. This confirmation removes the file from the active drill set, leaving TXT3 as the governing source for the drill report and the corresponding hole locations. Because the order specifies resin plugging and a 2-order HDI PCB structure, only the confirmed drill data will be used to generate the laser and mechanical programs. The ignore instruction also prevents any conflict between the DRR information displayed on TXT3 and residual coordinates that might have existed in TXT4. With the obsolete file excluded, the drill chart, the resin-plug map, and the subsequent plating to 18 µm hole-wall copper can be prepared from a single, customer-approved source.
HDI Drill Data Consistency Check
Before releasing the drilling programs, CAM engineers need to verify that the drill data are consistent with the layer structure and the intended via configuration. For this 6-layer, 2-order HDI board ( #HDI-20251022-0006 ), the presence of both TXT3 and TXT4 required additional attention because processing an outdated drill file could introduce unintended holes into the finished circuit.
The verification process should include checking the file revision, drill tool list, hole diameters, coordinates, and the correspondence between the drill data and the Gerber layer information. Particular attention should be given to the minimum 0.15 mm hole size, as even a small discrepancy in the active drill data can affect the intended via locations and subsequent plating operations.
After the customer confirmed that TXT4 was obsolete, the file was excluded from the manufacturing data. This illustrates an important CAM principle: when multiple drill files are present, engineers should obtain explicit revision confirmation rather than independently assuming which file is authoritative.
Acceptance of the Factory Stackup Structure
We prepared a stackup structure referenced to a prior build and asked the customer to confirm whether the attached construction was acceptable. The order form lists no customer stackup requirement and shows a 1.0 mm finished thickness with 1 oz copper. For a 2-order HDI the stackup defines the dielectric thicknesses through which the blind vias are laser-drilled after each sequential lamination; an unconfirmed dielectric gauge can place the laser features outside the process window or alter the final thickness.
The customer confirmed that the factory stackup was acceptable. This approval locks the core, prepreg, and copper arrangement for the Kingboard KB-6165F material at the 1.0 mm target. The confirmed structure supports the resin-plugged blind and buried vias while remaining compatible with the blue solder mask and the mechanical forming that includes both V-cut and routing on the customer-supplied 1×2 panel. Because no impedance control is required, the stackup confirmation serves primarily to fix the sequential build order and the dielectric distances used for laser drilling rather than to satisfy a controlled-impedance calculation. With the structure accepted, the lamination cycle and the corresponding sub-composite drill programs can be released.

Figure 3: final stackup structure
6-Layer HDI CAM Review: Drill Data Verification and Stackup Approval
The two confirmations address complementary prerequisites for releasing this 6-layer 2-order HDI board. Ignoring the obsolete TXT4 drill file ensures that only the current hole set—documented on TXT3—is manufactured, plated, and resin-plugged. Accepting the factory stackup establishes the dielectric construction through which those confirmed holes, particularly the laser-drilled blind vias, will be formed. Together they eliminate ambiguity in both the drill data and the lamination sequence.
Neither item could be resolved from the files alone. The presence of an extra drill file required an explicit ignore instruction, and the absence of a customer stackup required approval of the factory proposal. Once the customer confirmed that TXT4 could be ignored and that the attached stackup was acceptable, the active drill set and the sequential press cycle were defined. The board can then proceed through inner-layer imaging, sequential lamination according to the approved structure, laser and mechanical drilling of the confirmed holes, resin plugging, outer-layer processing, and mechanical forming with the V-cut and routing paths of the 1×2 panel. The case illustrates how CAM review of a 2-order HDI commonly includes a brief data-cleanup confirmation for residual drill files and a stackup approval when no customer construction is supplied, thereby aligning the manufacturing data with the intended 1.0 mm, resin-plugged build.